Bug #11627

[node manager] not assigning weights

Added by Peter Amstutz over 1 year ago. Updated over 1 year ago.

Status:
New
Priority:
Normal
Assigned To:
-
Category:
-
Target version:
Start date:
Due date:
% Done:

0%

Estimated time:
Story points:
-

Description

Node manager is supposed to assign a weight to compute nodes when they come up. The weight controls scheduling preference (prefer to schedule work on lower weight nodes). The weight currently uses price per hour * 1000. However, it seems that the process within node manager which is supposed to set the weight doesn't always run, as a result when we run "sinfo" the weight for most nodes is 1.

History

#1 Updated by Peter Amstutz over 1 year ago

  • Description updated (diff)

#2 Updated by Tom Morris over 1 year ago

  • Target version set to Arvados Future Sprints